Load, transport, offload, ON LOAD! The 2 x 3.15MVA transformers critical to power communities

Greenro Solutions :: News

The journey: Load, transport, offload, ON LOAD! The 2 x 3.15MVA transformers critical to power communities in the Western Cape and prevent power failures and loading issues.

This project re-emphasized the fact that, every project has its challenges, however simple it looks at the beginning. Do not take it for granted. But, it’s how you deal with the challenges, ensuring that client satisfaction and transparency are intact. It’s a people centered approach we have at Greenro Solutions At the end, the team did it and the client is very happy, and the communities will have improved power supply reliability.

Greenro Solutions
Greenro Solutions

La mise en place des solutions


Concevoir
  • • Stimuler le business
  • • Exigences
  • • Développer une proposition technique et commerciale
  • • Fournir un design conceptuel
  • • Préparer un design détaillé

Construire
  • • Approvisionnement
  • • Fabrication
  • • Installation
  • • Mise en service et certification

Surveiller et entrenteni
  • • Maintenance de routine
  • • Systèmes d’alerte rapide
  • • Maintenance réactive

Conseil / Consultation
  • • Évaluation/études du site
  • • Rapports du site
  • • Rapports de conformité